Public Works - Current Projects

Posted on: June 11, 2020

Pompano Reuse Irrigation Project- Updated 8/17/2020

Phase I installation is complete with individual meter hookups underway.

Phase II installation is complete with individual meter hookups underway.

Phase III installation is scheduled to begin in early March 2020

Phase III installation temporarily on hold due to Covid-19. 

More information about the City of Pompano Beach Oasis Reuse water program can be viewed on the City of Pompano Beach website