News Flash

Public Works - Current Projects

Posted on: September 3, 2020

Force Main Replacements (Broward County Project)- Updated 2/25/2021

This project will replace the aged sewer force mains running along NE 21st Way from NE 38th St to NE 39th St and along NE 22nd Avenue from NE 39th St to NE 44th St. The construction results in lane and road closures during the day with reopening upon completion each evening.

  • NE 21st Way (6"): Pipe installation complete, working on final tie in and asphalt restoration
  • NE 22nd Avenue (6"): Pipe installation complete
  • NE 44th Street (4"): Pipe installation complete
  • NE 22 Avenue (16' and 20"): 16" installation North of the master pump station has begun, this will result in daily daytime roadway closures

View the Force Main Replacement Notice (PDF).